MITHI REJUVENATION WORK – PHASE I & II - STATUS

Click here for Marathi

REMOVAL OF DEBRIS/SILT  

PHASE I (2005/06)

PHASE II (2006/07)

 

Target (Cu.m)

 

Removed (Cu.m)

Transported (Cu.m.)

Target (Cu.m)

Removed

(Cu.m.)

Transported

(Cu.m.)

MMRDA

-

  7,36,250

   7,35,250

 23,30,000

1,05,000

   19,750

BMC

-

  5,60,190

   4,13,600

   2,79,000

1,01,700

   84,500

Total

12,98,000

12,96,440

11,48,850

26,09,000

2,06,700

1,04,250

 

REMOVAL/DEMOLITION OF STRUCTURES & REHABILITATION 

PHASE I

PHASE II

 

Demolished

Rehabilitated

Target

Demolished & Rehabilitated

Residential

3314

 2201

4900

Nil

Commercial

  670

   376

  600

Nil

Total

3984

2577

5500

Nil

 

 